How to run an acceptance inspection and close the protocol

Acceptance inspections in Buildinio: checklist, point-by-point assessment, outcome, repair deadline and a PDF protocol. Failed points become issues and repair tasks.

Who it's for: the project manager, their deputy and the site manager.

What you'll do: plan an acceptance inspection or carry it out right away, assess the checklist points and close the protocol with an outcome. Failed points become issues (defects) and repair tasks with a deadline.

Before you start

  • The Acceptances module is available from the Company plan.
  • You can prepare a checklist template in the Checklist templates tab and reuse it in later inspections.
  • An acceptance can be just a note. The checklist, issues and repair deadline are optional.

Steps

  1. Go to Acceptances and click New acceptance. Choose what you're doing:
    • Planning for a day — the acceptance waits for its date (enter the Acceptance day),
    • Accepting now — you go straight to the inspection.
  2. Enter a name, e.g. “Plastering — ground floor”, and choose the Acceptance type (partial or final). Optionally add a Checklist, fill in What we inspect (schedule items) and Photos and notes. Click Save or Start the acceptance.
  3. In an acceptance with the In progress status, describe in the Protocol field what was checked and with what result.
  4. Assess every point on the list: passed or failed. Add missing points with Add a point. Each point can have a note, a photo and a voice note. As soon as one point fails, the outcome changes to With defects and the Repair by field becomes required.
  5. Click Close the protocol. The Closing the protocol window shows the outcome and a summary of what closing will create: how many issues and repair tasks, under which schedule item and with what deadline. You can't close the protocol until every point is assessed and, if there are defects, a repair deadline is set.
  6. If the inspection didn't happen, e.g. the work wasn't ready, tick I reject this acceptance. The “passed” and “with defects” outcomes follow from the checklist, so you don't choose them.

What happens next

  • The closed protocol version becomes a document: its text and photos can no longer be changed. Download it with Download protocol (PDF).
  • Failed points go to the Issues module, and repair tasks go to the schedule with the deadline from Repair by.
  • After the repairs, add the Next protocol version. It gets the points that failed and the deadline of the latest repair.
  • The acceptance appears on the Acceptances list with its type, number of protocol versions and the return date.

Troubleshooting

  • I can't close the protocol. Read the message in the closing window: some points are not assessed yet, or the repair deadline is missing.
  • No repair tasks were created after closing. On a plan without the schedule module, only issues are created. The closing window warns you about it before you confirm.

See it on your own project